Cost Overruns in Infrastructure Projects
April 3, 2025
The risk involved in an infrastructure project does not remain the same throughout the life of a project. Instead, the risk varies depending upon the stage in which the project is. The construction phase is supposed to be the riskiest phase of an infrastructure project. This is also the phase where investors demand the highest…
In the previous article, we explained the concept of cost overrun. We also explained how cost overruns have a negative effect on the finances of the entire project. However, it is strange that despite being so harmful to infrastructure projects, cost overruns are still ubiquitous. It is common for more than 50% of megaprojects to…
Infrastructure finance is an extremely complicated and advanced field. There are many complex financial instruments related to infrastructure finance which have been created and are regularly traded between interested parties. One such financial instrument is the collateralized debt obligation (CDOs). The issuance of CDOs is the most basic way in which the principles of structured…
A contract is said to be well formed if it is able to cover all the possibilities and provide guidance about what will happen in each and every situation. However, this benchmark cannot really be applied to PPP contracts used for building infrastructure projects. This is because infrastructure projects are extremely long term in nature. They tend to continue for years and sometimes even decades.
Hence, no matter how much due diligence is followed, it is impossible to predict the possible outcomes with any reasonable degree of certainty. Hence, preparing for these possible outcomes is also difficult, if not impossible. Therefore, when it comes to infrastructure projects and contracts, a good contract allows adjustments to be made with mutual consent of all the parties involved.
There are various types of PPP provisions which are open to adjustment in PPP contracts. Some of these provisions have been listed in the article below:
The degree to which one party can modify the contract is based on the type of disruption being faced and also the severity of such disruption. Also, before entering into the contract, a financial model is decided which gives either operator the authorization to modify key financial terms in a contract to a reasonable degree. The upper and lower limits of these modifications are decided in advance. The basic idea is that no party should be at a disadvantage because of the long term nature of infrastructure contracts.
The price of the service as well as the scope of the service to be provided may change rapidly based on factors beyond the control of the service provider. PPP contracts must have adjustment mechanisms in place in order to deal with such changes.
The autonomy with which the changes can be made is decided based upon who is initiating the changes as well as the scope of the changes being requested. Service providers may include small tasks without levying any additional charges. On the other hand, they may even agree to forego certain changes if the changes they are proposing put them in an advantageous position.
In other contracts, something as simple as the government provided inflation numbers are used to modify the tariffs. Also, in some contracts, tariffs are changed every year whereas in other contracts changes are triggered based on external circumstances which are specified in the contract.
In many projects, there might not be any tariffs. In such cases, costs are benchmarked with the inflation rate. This is because the outflow of cash from the government to the contractor need to be adjusted to reflect the escalating costs.
In most cases, simple indexation does not work. Suppliers are not willing to provide services if their revenues will increase only by the indexed numbers. This is because over the long run, the actual inflation is far greater than the government provided inflation numbers. As a result, the service providers would actually be at a loss if they accepted the terms.
A good PPP contract must have provisions which allows the refinancing of debt to reflect the current risk which is present in the business. In some cases, the contract requires the gain from refinancing to be split between the old creditors and the infrastructure company.
The basic idea is that the contract must be drafted in such a way that both parties are considerate towards the need of one another. If one party uses external circumstances to try to usurp the needs of the other, the contract should be able to prevent that.
Your email address will not be published. Required fields are marked *